Capital Improvement Projects
Capital Improvement Projects
The Capital Improvements Program (CIP) is a listing of priority projects that are intended to meet City Council's goal of upgraded city infrastructure and facilities. Upgrades come in the form of new facilities or infrastructure, or maintaining the current investment for the benefit of Northglenn residents. CIP projects help to maintain streets, parks, buildings, sanitary wastewater system, water distribution systems, water and wastewater treatment facilities, traffic control devices, stormwater tributaries and other assets.
In order to be included in the CIP, a project must meet the following requirements:
• Total costs of the project are expected to meet or exceed $5,000.
• The resulting project will have a useful life of more than one year.
• The project will result in the creation of a new asset or the extension of an existing asset’s useful life, value, and/or operational capacity.
Projects
Sanitary Sewer Manhole Rehabilitation
This CIP includes the rehabilitation of sanitary sewer manholes throughout the city. The project uses a four-part process to build back the structural strength of the manhole and seal the manhole from infiltration and prevent deterioration from corrosive sanitary sewer flows. The anticipated start of construction is June 2012
2012 Concrete Replacement Project
This CIP includes the replacement of deteriorated concrete in miscellaneous locations throughout the city. The project also includes the replacement of concrete on the Greenway Trail System. This project is anticipated to begin in July 2012.
2012 Traffic Signal Improvements
This project will clean and paint select traffic signal poles and install countdown pedestrian indicators at select intersections. This project is anticipated to begin in August 2012.
High Zone Water Meter Vault
This CIP project includes the installation of a concrete vault and water meter on the high zone water transmission line in front of the Water Treatment Plant. The anticipated start of construction is May 2012.
Grange Hall Creek - Washington Street Detention - Phase 1
This capital improvement project is a cooperative agreement between the Urban Drainage & Flood Control District and the city of Northglenn. It includes improvements to the drainage channel and the installation of a pedestrian underpass that also serves as a part of the drainage improvements. Construction is anticipated to begin in the fall of 2012 and should be complete by the fall of 2013.
2012 Street Improvements
This project will resurface:
• East 105th Avenue from Lincoln Court to Grant Drive
• Claude Court from East 120th Avenue to East 112th Place
• A portion of Spangler Drive
• West 101st Avenue from Pecos Street to Croke Drive
This project is anticipated to begin in July 2012.
Water Treatment Facility Improvements
This project includes the addition of sodium permanganate storage and feed equipment to improve the removal of manganese and the addition of a rapid mix chamber and dual flocculation basins to improve the removal of total organic carbon. These upgrades will improve the taste of drinking water during the months of August and September and allow the facility to meet stricter drinking water regulations that come into effect in October 2013. Construction is scheduled to start in September 2012 and be completed in August 2013.
